Heavy Civil

Stoney & 11th Interchange Roadway Construction

Ironclad partnered with PCL Construction to deliver a new roadway and interchange project that required significant earthworks planning and management to successfully achieve an aggressive project schedule.

KEY DETAILS

Contract Value

$2,084,134

Project Owner

The City of Calgary

Completion Date

June 2024

Project Role

Subcontractor

Scope of Work

  • Topsoil stripping to stockpile.
  • Erosion control measures.
  • Complete construction of crossovers. 
  • Common excavation across highway.
  • Culvert installation and riprap swales.
  • Subgrade preparation for concrete slope protection.
  • Topsoil placement and final seeding.
No items found.

Resources & Challenges

  • Total Crew: 10 Persons
  • Equipment Used:
    2 Excavators, 4 Rock Trucks, 6 Scrapers, 2 Compactors, 2 Dozers, 1 Grader, 
18 Highways Trucks.
  • Challenges:
    The project required detailed take-off and quantity analysis to deliver the most effective earthworks management plan that resulted in completion of the aggressive project schedule on time.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL

In earthworks, unforeseen issues often arise beyond contract documents. It's reassuring to know that Ironclad has the know-how to plan properly and get the job done.

Kaden Dauter, Estimator, PCL Construction | Stoney & 11th Interchange Roadway