Heavy Civil

Cougar Creek Flood Debris Retention Structure

Ironclad Earthworks acted as the prime contractor for the Cougar Creek Flood Debris Retention Structure project in Canmore, Alberta. This project involved constructing a significant flood mitigation structure to protect the area from debris floods.

KEY DETAILS

Contract Value

$20,583,345

Project Owner

Town of Canmore

Completion Date

August 2024

Project Role

Prime Contractor

Scope of Work

  • Construction of a 50-meter-high rock-filled embankment dam with upstream and downstream faces covered by soil and seeded.
  • A 20-meter-wide rock-cut spillway on the east abutment with wildlife egress areas.
  • Drilling and pressure grouting.
  • Embankment construction with a sheet pile core wall built within the bedrock.
  • Rock blasting and processing.
  • Dewatering and pumping.
  • Earthworks.
  • Topsoil placement and hydroseeding.
  • Reinforced cast-in-place concrete structures.

No items found.

Resources & Challenges

  • Total Crew: 45 Persons
  • Equipment Used:
    12 Excavators, 8 Rock Trucks, 4 Dozers, 4 Compactors, specialized equipment for grout curtain drilling and installation, and drilling and blast operations.
  • Challenges:
  • A tight schedule requires completion before the upcoming flood season.
  • Managing to change ground conditions to balance material requirements for the flood retention structure.
  • The project required 24-hour workdays and seven-day workweeks for three consecutive months to meet the aggressive schedule.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL

Ironclad successfully completed three high-quality projects for the Town of Canmore, including the complex Cougar Creek dam. I look forward to working with them again.

Félix Camiré, Project Engineer, Town of Canmore | Cougar Creek Project