Instream Works

Fairmont Creek Flood Diversion and Mitigation

Ironclad was prime contractor on the Fairmont Creek Flood-Debris Mitigation project for the Regional District of East Kootenay, providing general contracting, waterworks construction, and road construction services.

KEY DETAILS

Contract Value

$1,740,000

Project Owner

Regional District of East Kootenay

Completion Date

December 2018

Project Role

Prime Contractor

Scope of Work

  • Tree clearing.
  • Access road construction.
  • Common excavation of over 20,000 m3 and 6,000 m3 of aggraded creek bed sediment.
  • Two sediment trap basins.
  • Construction of five rock weirs using on-site salvaged rock.
  • Import of 4,000 tonnes of over-sized riprap.

No items found.

Resources & Challenges

  • Total Crew: 10 Persons
  • Equipment Used:
    3 Excavators, 4 Rock Trucks, 2 Dozers, 1 Compactor, 8 Highway Trucks.
  • Challenges:
    The project faced challenges due to its proximity to the Fairmont Hot Springs Resort during peak season, necessitating strict traffic management and frequent work shutdowns for visitor events. Additionally, higher-than-average in-stream water flows required a comprehensive water and turbidity management strategy.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning