Demolitions
Stoney 22X Bridge Demolition and Instream Berm Works
Ironclad partnered with PCL Construction for the demolition of a 6-span bridge on Stoney Trail over the Bow River that required a significant instream berm to complete the works.
KEY DETAILS
■
Contract Value
$2,563,194
■
Project Owner
Alberta Transportation
■
Completion Date
July 2024
■
Project Role
Prime Contractor
Scope of Work
- Traffic accommodation.
- Asphalt milling.
- Bridge demolition.
- Disposal of contaminated materials.
- Common excavation.
- Asphalt paving.
- Site restoration.
Resources & Challenges
- Total Crew: 8 Persons
- Equipment Used:
2 Excavators, 1 Loader, 1 Skidsteer, 1 Dozer, 1 Compactor, 8 Highway Trucks.
- Challenges:
The project was challenged by an aggressive schedule that required the instream berm construction and bride demolition to be completed very quickly. Ironclad responded with two crews that had the required experience to complete both scopes with perfection.