Commercial Buildings
Bridgeland Continuing Care Facility Construction
Ironclad partnered with Clark Builders to deliver the successful construction of a 275,000 square foot continuing care facility in the neighborhood of Bridgeland.
KEY DETAILS
■
Contract Value
$2,700,605
■
Project Owner
Alberta Infrastructure
■
Completion Date
September 2024
■
Project Role
Subcontractor
Scope of Work
- Site demolition and disposal.
- Bulk excavation of foundation.
- Detailed excavation and backfill.
- Slab-on-grade preparation.
- Mechanical excavation and backfill.
- Contaminated material disposal.
- Final site grading.
Resources & Challenges
- Total Crew: 12 Persons
- Equipment Used:
3 Excavators, 1 Loader, 2 Skidsteers, 1 Dozer, 2 Compactors, 16 Highway Trucks.
- Challenges:
Ironclad cooperatively worked on a busy construction site with stacked subtrades working with multiple crews to deliver a large commercial excavation project.