Commercial Buildings
BRIO Brentwood Village Excavation and Site Preparation
Ironclad was subcontracted by CANA Construction for the Brentwood Village project, providing high-rise foundation excavation, commercial excavation, and environmental remediation.

KEY DETAILS
■
Contract Value
$1,132,142
■
Project Owner
BRIO Brentwood
■
Completion Date
December 2019
■
Project Role
Subcontractor
Scope of Work
- Bulk excavation for a high rise foundation.
- Dewatering.
- Backfill in winter conditions using 40mm drain rock.
- Detailed excavation and backfill.
- Final site grading.
Resources & Challenges
- Total Crew: 10 Persons
- Equipment Used:
3 Excavators (1 Long Reach), 1 Loader, 1 Skidsteer, 1 Dozer, 16 Highway Trucks.
- Challenges:
The project faced challenges with potential contaminated material during excavation, requiring close coordination with soil testing consultants. Additionally, its location in a high-traffic area demanded strict accommodation measures.