Heavy Civil
James Walker Trail Bridge and Earthworks Development
Ironclad partnered with PCL Construction to complete all earthworks on this challenging transportation infrastructure project. Ironclad successfully finished the project on schedule and was an invaluable partner when it came time to construct a significant in-stream river berm to allow for pier construction of the new bridge.
KEY DETAILS
■
Contract Value
$2,175,000
■
Project Owner
Town of Cochrane
■
Completion Date
October 2019
■
Project Role
Subcontractor
Scope of Work
- Topsoil stripping to stockpile.
- Common excavation to embankment.
- Bulk Import material from off-site.
- In-stream berm with riprap protection.
- Detailed excavation & backfill for structure.
- Seeding and ESC measures.
Resources & Challenges
- Total Crew: 15 Persons
- Equipment Used:
3 Excavators, 5 Rock Trucks, 2 Dozers, 2 Compactors, 1 Loader, 1 Skidsteer, 20 Highways Trucks.
- Challenges:
Completion of large in-stream berm on Bow River with all materials imported and placed in real time during short fish window.